There are two established ways to buy an office fit-out. With design and build, one company designs the space and builds it. With the traditional route, you hire a design team, they complete the design, and contractors compete to build it. Design and build is quicker and simpler. Traditional gives you more independent control. Most fit-outs under about 20,000 sq ft are done by design and build; most very large or complex ones are not.
How each works
Design and build. You brief two or three fit-out companies. Each proposes a design and a price. You choose one and sign a single contract for both design and construction. Their designers, engineers and site team work as one, and construction can begin before every detail is drawn.
Traditional. You appoint an interior designer or architect, usually with a services engineer, a cost consultant and a project manager. They design the scheme in full and produce tender documents. Several contractors price exactly the same documents. You appoint one, and your design team inspects their work as it proceeds.
Side by side
| Design and build | Traditional | |
|---|---|---|
| Contracts | One | Several |
| Time before starting on site | Shorter: design and pricing overlap | Longer: full design, then four to eight weeks of tender |
| Price certainty | A fixed price early, on an incomplete design | A firm price later, on a complete design |
| Comparing bids | Harder: different designs at different prices | Easier: same design, different prices |
| Responsibility for design errors | The contractor | Shared between designers and contractor |
| Independent quality check | Only if you appoint one | Built in |
| Professional fees | Within the contract price | Paid separately, commonly 10% to 15% of build cost |
| Changes during the works | Quick to agree, priced by the contractor | Slower, checked by your cost consultant |
Where design and build wins
Speed. With one team and overlapping stages, a small project can go from brief to site in weeks. If your lease event is close, this often settles the question.
Simplicity. One contract, one point of contact, one company to hold to account. If the air conditioning does not work, there is no argument about whether the fault lies with the design or the installation.
Buildability. The people who will build it are in the room when it is designed, so impractical or expensive details are caught early.
Cost for smaller jobs. Avoiding a separate professional team keeps fees down on projects where they would be out of proportion.
Where traditional wins
Like-for-like competition. Every contractor prices the same drawings, so you can see who is cheapest for an identical result.
Independent advice. Your designer and cost consultant work for you. They have no interest in specifying what is easiest or most profitable to build.
Design depth. A design team working without a contractor's margin in mind will often push further on quality and detail.
Governance. Organisations that must demonstrate competitive tendering, such as public bodies, charities and regulated firms, usually need this route.
The risks of each
With design and build, the same company sets the specification, the price and the standard of inspection. Most act responsibly. But the commercial incentive is to meet the letter of the brief at the lowest cost, so the quality you get depends on how precisely the contract documents describe what you expect. Vague documents produce cheaper partitions, simpler joinery and thinner carpet than you thought you had bought.
With traditional, the risk is time and cost surprise. You spend months and fees on a design before any contractor tells you what it costs to build. If tenders come back over budget, you redesign, with the clock running. A good cost consultant makes that less likely. It still happens.
The middle ground
Many occupiers combine the two.
- Design and build with an independent adviser. A project manager or cost consultant on your side writes the brief, runs the competition, checks the price and inspects the work. A modest fee for most of the protection of the traditional route.
- Two-stage tendering. A contractor is appointed early on fees and overheads, helps finish the design, then agrees a fixed price. Faster than traditional, with more transparency than a single-stage bid.
- Detail and build. You hire a designer for the concept, then hand it to a design and build contractor to complete and construct. Useful when the look matters most to you.
Which suits you?
Choose design and build if most of these apply:
- The project is under about 20,000 sq ft
- The move-in date is tight
- You want one company responsible for everything
- You have a clear brief and a fixed budget
- You do not have in-house property expertise
Choose traditional if most of these apply:
- The project is large, technically complex or in a listed building
- You must show a formal competitive tender
- Design quality is the priority, and you have time
- You have, or will hire, people to manage a professional team
Whichever you choose
Three things protect you on either route. Write a proper brief before anyone draws anything; the design brief questionnaire will get you most of the way. State your budget, so that proposals can be compared. And check the company as carefully as the design, using the method in how to choose a fit-out partner.
The route also changes your programme. The timescale calculator lets you switch between the two and see the difference in start dates.