An office move is won or lost in the months before it happens. This checklist sets out what to do and when, counting back from move day. It assumes you are taking leased space and fitting it out. If you are moving into a serviced or managed office, you can skip most of the first two sections.
Dates are for a mid-sized office. Larger moves need longer at every stage, and the timescale calculator will give you dates for your own size.
12 months or more before
- Find your lease expiry or break date, and the notice you must give
- Decide whether to move, stay or refurbish, and get the board's agreement in principle
- Appoint one person to lead the project, with time to do it
- Work out how much space you need and set an outline budget
- Appoint a tenant-side agent and a solicitor
- Ask a surveyor for an estimate of dilapidations on your current office
9 to 12 months before
- Agree the brief: location, size, quality, lease length, must-haves
- View buildings and draw up a shortlist
- Get a test fit and an outline fit-out cost for each shortlisted building
- Bring in a designer or fit-out company to advise before you commit
- Check which internet carriers serve each building
6 to 9 months before
- Agree heads of terms, including rent-free period and reinstatement obligations
- Instruct solicitors on the lease
- Develop the design and agree the layout
- Send drawings to the landlord for consent as early as possible
- Order the internet line as soon as you have a confirmed address
- Tell staff the move is happening, and why
3 to 6 months before
- Sign the lease and obtain the licence to alter
- Appoint the fit-out contractor and agree the programme
- Order furniture and anything else with a long lead time
- Get three quotes from commercial removal companies and book one
- Audit furniture and equipment: what moves, what is replaced, what goes
- Give notice on contracts tied to the old office: cleaning, plants, water, vending, print
- Decide between doing dilapidations works and negotiating a settlement
- Set up a staff working group, with one representative from each team
2 to 3 months before
- Agree the seating plan and share it
- Plan the IT move in detail. The IT and telecoms checklist covers it
- Arrange insurance for the new premises and for goods in transit
- Order new signage, stationery and access passes
- Book lifts, loading bays and parking suspensions at both buildings
- Start clearing: archive, shred, sell, donate
- Arrange facilities contracts for the new office
4 to 8 weeks before
- Confirm the fit-out completion date and walk the site
- Confirm the internet line is installed and tested
- Issue a move guide to staff: dates, what to pack, what to take home, where they will sit
- Tell clients, suppliers, banks, insurers, HMRC and Companies House the new address and the date it takes effect
- Set up mail redirection
- Arrange a deep clean of the new office after the builders leave
- Arrange clearance and cleaning of the old one
The final 2 weeks
- Crates and labels delivered; packing instructions repeated
- Every desk, crate and piece of equipment labelled with its destination
- Inspect the new office with the contractor and agree the list of defects
- Take handover: keys, passes, manuals, test certificates, drawings
- Confirm the move-day plan with the remover, IT team and both building managers
- Circulate a contact sheet with mobile numbers for everyone involved
- Back up all systems
Move weekend
- A named person in charge at each building
- Protect floors, doors and lifts before anything moves
- IT kit goes first and is set up before desks are populated
- Check each area against the floor plan as it is completed
- Test internet, Wi-Fi, phones, printers, door access and meeting room screens
- Walk the old office once it is empty and photograph it
- Walk the new office before anyone goes home, and fix what can be fixed
The first week
- Welcome people properly: a floor plan on every desk, someone to ask, and coffee
- Have IT support and a furniture fitter on the floor, not on the end of a phone
- Keep one list of problems and work through it daily
- Unpack to a deadline and return the crates
- Chase the contractor on defects while they are still on site
The first three months
- Hand back the old office in the condition the lease requires, on time
- Settle dilapidations
- Cancel remaining services at the old address
- Ask staff what is working and what is not, and act on the top issues
- Review the final cost against the budget
- File the drawings, manuals and warranties where your successor will find them
The five things most often forgotten
- The internet line. Ordered too late more often than anything else on this list.
- The old office. Emptying and reinstating it is a project of its own.
- Landlord consent. The contractor cannot start without it, and you do not control how long it takes.
- Address changes. Banks, payroll, insurers, registered office, software licences.
- Telling people. Staff who hear about the seating plan from a floor plan on the wall do not forgive it.
For how the stages fit together, read office relocation, step by step.