From deciding to move to the first day in the new office, allow about six months for a small office, nine to twelve for a mid-sized one and eighteen months or more for a large one. Moving into a serviced office can be done in weeks. Taking a lease and fitting out the space cannot.
Most of that time is not building work. It is searching, negotiating, lawyers and waiting for approvals.
Typical programmes by size
These are planning allowances for a move into leased space with a new fit-out, bought through design and build.
| Stage | Under 5,000 sq ft | 5,000 to 15,000 sq ft | 15,000 to 40,000 sq ft |
|---|---|---|---|
| Brief, budget and team | 3 weeks | 4 weeks | 6 weeks |
| Property search | 6 weeks | 8 weeks | 12 weeks |
| Heads of terms | 2 weeks | 3 weeks | 4 weeks |
| Legals, alongside design | 6 weeks | 8 weeks | 10 weeks |
| Fit-out works | 6 weeks | 10 weeks | 14 weeks |
| Furniture, IT and move | 2 weeks | 3 weeks | 4 weeks |
| Total | About 25 weeks | About 36 weeks | About 50 weeks |
A traditionally tendered fit-out adds a tender period and more time on site, typically one to three months in all.
What takes the time
The search. Finding a building is quick. Finding the right one, at the right price, with a landlord who will agree terms, is not. Allow longer if you need a particular postcode or an unusual size.
The legal process. Once terms are agreed, solicitors on both sides negotiate the lease. Six to eight weeks is normal and three months is not unusual. Your fit-out drawings also need the landlord's formal consent, and contractors cannot start until they have it.
Lead times. Some things simply take as long as they take. A new business internet line commonly needs around three months. Furniture is usually six to twelve weeks from order. Glazed partitions, air conditioning equipment and bespoke joinery can be similar.
Your own decisions. Board approvals, budget sign-off, choosing between layouts. On many projects the client's decision time adds more weeks than any contractor does.
Work backwards from the lease
The date that matters is usually the end of your current lease, or a break date. Count back from it.
- Move-in date. Set it at least a month before you must be out of the old office, to leave time for clearing and reinstatement.
- Start on site. Move-in date, less the fit-out and furniture period.
- Lease signed and consent in hand. The day before the contractor starts.
- Heads of terms agreed. Two to three months before that.
- Search started. Two to four months before that.
- Brief written and advisers appointed. A month or two earlier still.
For most businesses that lands twelve to eighteen months before the lease event. If your lease has a break clause, the notice date comes even earlier, and it is unforgiving: miss it and the option is gone.
Ways to go faster
If the dates do not work, there are four real options, each with a cost.
- Take fitted space. A floor the landlord has already fitted out, or a managed office, removes most of the design and build period. You give up control over the layout.
- Choose design and build. One company designing and building overlaps stages that a traditional tender runs in sequence.
- Start design before the lease is signed. Common and sensible, provided you accept that the design fees are at risk if the deal falls through.
- Buy time on the old lease. A short extension or holding over by agreement is often cheaper than a rushed fit-out. Ask early; landlords with a new tenant lined up will say no.
What does not work is asking the contractor to build faster after everything else has run late. Compressing the site period means overtime, mistakes and a move into an unfinished office.
Signs you are already late
- Your lease event is under nine months away and you have not started a search
- You have agreed terms on a building without a test fit or a budget
- Nobody has ordered the internet line
- The landlord has not yet seen your drawings and the contractor is due on site next month
None of these is fatal. Each one is a reason to take advice this week.
For the full sequence, see office relocation, step by step. For what to do in the final months, see the office move checklist.