How to build an office move budget your finance director will sign

Costs and budgets. 6 minute read. Published 25 November 2026.


A move budget that survives a board meeting has seven lines: the fit-out works, furniture, technology, the move itself, exit costs on the building you are leaving, professional fees and a contingency. Miss any one of them and the number you present will be wrong by a wide margin.

The most common failure is not underestimating the fit-out. It is forgetting the old building.

The seven lines

Rates below are per sq ft of the new office, at central London levels, excluding VAT. Outside London, multiply by about 0.93 for Greater London and the South East, 0.84 for a regional city and 0.78 for the rest of the UK.

LineTypical rangeNotes
Fit-out works£80 to £115 per sq ftA standard specification. Essential is nearer £60 to £85, premium £155 to £250.
Furniture£25 to £40 per sq ftMid range. Reusing what you have drops this to almost nothing.
Technology and AV£7 to £12 per sq ftVideo calls in every meeting room. Basic Wi-Fi and a few screens is £3 to £7.
The move£2 to £5 per sq ftCrates, porterage, weekend working, a few redundant items.
Dilapidations£10 to £30 per sq ft of the old officePutting the building you are leaving back as the lease requires.
Professional feesAbout 10% of the worksProject manager, designer, cost consultant, building control.
ContingencyAbout 10%Not optional. It is the line that stops the others becoming a problem.

Why dilapidations catch people out

Dilapidations are charged on the floor area you are leaving, not the one you are taking. A business moving from 8,000 sq ft into 5,000 sq ft is budgeting the fit-out on 5,000 and the exit on 8,000.

It is also the one line that is already a liability. The obligation exists whether or not you have budgeted for it, and the landlord will raise a claim whether or not you have money set aside. Get a surveyor to look at your lease and the building early. A schedule of dilapidations is negotiable; being surprised by one is not.

The three questions you will be asked

"Is this capital or revenue?" Most fit-out spend is capital. Some of it may attract capital allowances, and the split between what does and does not is worth getting right before you commit, not after. Your accountant will want the cost plan broken down in a way that lets them make that call.

"What happens to it at the end of the lease?" Fit-out you install usually has to come out again unless the landlord agrees otherwise. That is worth negotiating in the heads of terms, before the lease is drafted, because a licence to leave the fit-out in place removes a future cost.

"What is the number if we do nothing?" Staying put is not free. Add up the dilapidations you will owe anyway, any refurbishment the current space needs, and the cost of the space you are paying for and not using. Often the comparison is much closer than it first looks.

Build it in the right order

  1. Size the space first. Every rate above is per sq ft, so the area drives everything. Work it out before you price anything.
  2. Choose a specification honestly. Decide what the office has to do, then pick the standard that matches. Pricing "standard" and building "enhanced" is the usual route to an overspend.
  3. Price the exit at the same time as the entry. Same meeting, same spreadsheet.
  4. Add fees and contingency last, as percentages. If the works number moves, they move with it.
  5. Give the board a range, not a point. A single figure invites the question "is that exact?" A range invites the question "what moves it?", which is the conversation you want.
Everything here is a planning allowance, not a quotation. Real prices come from a real building, a real drawing and a real contractor.

To size the space before you price it, use the office space calculator. For what drives the works rate up and down, see how much does an office fit-out cost. For the full sequence, see the moving office guide.