From appointing a designer to moving in, allow about 15 weeks for a small office fit-out, 24 weeks for a mid-sized one and 34 weeks for a large one, using design and build. A traditional tender adds roughly two months.
That is the fit-out alone. It does not include finding the building or negotiating the lease.
Design and build programmes
| Stage | Under 5,000 sq ft | 5,000 to 15,000 sq ft | 15,000 to 40,000 sq ft |
|---|---|---|---|
| Design and costing | 4 weeks | 6 weeks | 10 weeks |
| Landlord consent | 4 weeks | 6 weeks | 8 weeks |
| Fit-out works on site | 6 weeks | 10 weeks | 14 weeks |
| Furniture, IT and snagging | 1 week | 2 weeks | 2 weeks |
| Total | About 15 weeks | About 24 weeks | About 34 weeks |
Over 40,000 sq ft, allow 14 weeks design, 8 consent, 20 on site and 3 to finish.
What a traditional route adds
With a traditional contract the design is finished first, then contractors price it, then one is appointed. That tender period is 4 weeks on a small job and up to 10 on a large one. The site period also runs longer, because the contractor is building someone else's design and every query goes back through the designer.
As a rule of thumb, a traditional route takes about a quarter longer on site plus the tender period on top. You get a more competitive price and a clearer audit trail, which is why public sector and large corporate projects still use it.
Refurbishing while you occupy
Building around people who are still working takes about a fifth longer than building in an empty space. The work has to be phased, the noisy parts move out of hours, and each section has to be handed back clean and safe before the next one starts.
The things that actually cause delay
Landlord consent. Your drawings need a formal licence to alter. The landlord's surveyor and solicitor both get involved, and neither of them is working to your programme. Submit early and chase.
Long-lead items. Air conditioning equipment, glazed partitions, bespoke joinery and switchgear can all take longer than the site period they are needed in. The contractor should flag these in week one.
The internet line. A new business connection routinely takes around three months. It is ordered by you, not the contractor, and it is the single most common reason a finished office cannot open.
Your own decisions. Sign-off on the layout, the finishes, the furniture. On most projects the client takes longer than any trade.
Changes after start on site. Moving a wall on a drawing costs an hour. Moving it after the frame is up costs a fortnight.
How to compress it honestly
- Start design before the lease completes, accepting that fees are at risk if the deal fails
- Submit for landlord consent on an early drawing set rather than the final one
- Order long-lead items first, as a separate early package
- Take a floor that is already fitted, which removes most of this programme entirely
- Order the internet connection the day you agree heads of terms, not the day you sign
What does not work is asking the contractor to absorb everyone else's delay. A compressed site period means overtime, defects and moving into an unfinished office.
Work the dates backwards from your lease event with the timescale calculator. For the whole process, see the moving office guide.