Lease expiring in twelve months: what to do now

Property and leases. 6 minute read. Published 25 November 2026.


With twelve months left on an office lease you still have enough time to move, but not much slack. A mid-sized relocation with a new fit-out takes around nine months from a standing start, and that assumes nothing goes wrong. Start this month.

If you want to stay, twelve months is comfortable. If you want to move, it is tight.

The first two weeks

Read the lease. Specifically: the expiry date, any break clause and its conditions, the notice you must give, whether you have security of tenure under the Landlord and Tenant Act 1954, and what the reinstatement clause requires you to put back.

Get a dilapidations view. A building surveyor walking the floor will tell you roughly what the exit will cost. Allow £10 to £30 per sq ft of your current space until you have better information. That number changes the whole decision.

Decide who is deciding. One person responsible, a short list of people who must approve, and a date for the decision.

Work out what you need before you look at buildings. Size it from your busiest-day attendance, not your headcount, and set a budget range.

Then run three options in parallel rather than in sequence:

  • Stay and renegotiate. Often the cheapest outcome, and your landlord would rather keep you than find someone new. Ask early.
  • Stay and refurbish. Fixes a layout problem without the cost and risk of moving.
  • Move. Start the search now. Finding the right building takes six to twelve weeks before you even agree terms.

Months 9 to 6: terms and legals

Agree heads of terms on your preferred option. Solicitors then take six to ten weeks on the lease, and your fit-out drawings need the landlord's consent alongside it.

Run design at the same time as the legals. It is the only way the dates work, and it is normal practice.

Order the internet connection as soon as terms are agreed. Around three months is routine for a new business line, and it does not care that your fit-out finished early.

Months 6 to 1: build and move

Fit-out works run six to fourteen weeks depending on size. Furniture needs six to twelve weeks from order. Book the removal company around two months out, earlier if you need a month-end weekend.

Leave at least two weeks between practical completion and the move. Something always needs fixing.

Give yourself an overlap

Try to keep the old lease running for two to four weeks after you move. It gives you time to clear, strip out and hand back properly, and it is far cheaper than a rushed exit and a disputed dilapidations claim.

If you are already later than this

  • Six to nine months: a move is still possible into fitted or managed space. A full fit-out in a new building is unlikely.
  • Under six months: talk to your landlord about a short extension or holding over. Rushing a fit-out costs more than the extra rent.
  • Break clause notice date approaching: this is the urgent one. Break conditions are strictly applied and a missed deadline cannot be fixed. See break clauses: how tenants lose them.
This is general information, not legal advice. Lease terms vary and the consequences of getting notice wrong are serious, so take advice on your own lease.

Check whether your dates work with the timescale calculator, and see the moving office guide for the full sequence.

Want a second opinion on your numbers?

Tell us about your project and we will introduce one specialist for each service you ask for. You are under no obligation.

Ask a specialist