Furniture lead times and how to plan around them

Furniture. 5 minute read. Published 25 November 2026.


Allow six to twelve weeks between placing a furniture order and delivery, depending on the size of the order. Bespoke items, specific fabrics and anything imported take longer. Order before the fit-out is finished, not after.

Furniture is the item most likely to be late, because it is usually the last thing decided and the first thing forgotten.

Typical lead times by order size

Office sizeAllow from order to delivery
Under 5,000 sq ft6 weeks
5,000 to 15,000 sq ft8 weeks
15,000 to 40,000 sq ft10 weeks
Over 40,000 sq ft12 weeks

These are planning allowances for a standard range from stock finishes. They are not a quotation and they assume a supplier who already has your order confirmed.

What makes it longer

Bespoke joinery and reception desks. Made for you, so add weeks, and add a drawing approval stage before manufacture even starts.

Non-standard fabrics or finishes. A standard chair in a standard fabric may be in stock. The same chair in your brand colour is a production run.

Imported items. Shipping, customs and the risk of a container being late.

Large single orders. A manufacturer making 400 identical desks has to schedule a production slot.

Approval delays at your end. The clock usually starts when the order is signed off, not when you first discussed it. Every week you spend deciding is a week added.

When to place the order

Work back from the day you need the furniture in the building, which is after practical completion of the fit-out and before the move:

  1. Find your fit-out completion date
  2. Subtract the lead time above
  3. Subtract two weeks for sample approval and final sign-off
  4. That is your order date

For a mid-sized office with a 24-week fit-out programme, the furniture order usually needs placing around the middle of the works, not at the end.

Order the long-lead items separately and earlier. A reception desk or bespoke tea point joinery does not have to wait for the rest of the schedule to be agreed.

When it is going to be late

It happens. The options, in order of preference:

  • Hire for the gap. Furniture hire exists for exactly this and is cheaper than delaying a move.
  • Take a partial delivery. Desks and chairs first, meeting and breakout furniture later. People can work without soft seating.
  • Substitute a stock item in a different finish for the late pieces, and swap later if it matters.
  • Delay the move, which is usually the most expensive option because it touches the lease, the removals booking and everyone's diary.

What does not work is moving in and hoping. An office with no chairs is not an office.

Reusing what you have

Reused furniture has no lead time, which is a genuine advantage on a tight programme as well as a saving. Audit what you own early: what fits the new layout, what is worth moving and what should go. Deciding this late is how businesses end up paying to move furniture they then throw away.

Price furniture alongside the rest of the move with the budget calculator, and check the dates with the timescale calculator.

Want a second opinion on your numbers?

Tell us about your project and we will introduce one specialist for each service you ask for. You are under no obligation.

Ask a specialist